Sunday, May 3, 2009

Project Launch

Works in the construction of Bani Walied Industrial Zone (BWIZ) project started on 18.04.2009.

Owner: Authority of Industrial Zones (Libya)

Contractor: Kasaba Engineering

Contract value: LYD 1,318,500.000

Contract period: 7 months





Progress: Works started in excavation of foundations. It is a semi rock soil and jack hammers were used to excavate the foundations. Total number of footings is 600 and about 70% were finished. Each footing is about 1.2x1.2m and 0.5 m depth. Work has been also started in the preparation of reinforcement steel. Concreting will be commenced soon.